Original · GridDigest
Ark Energy wins grid approval for 435MW NSW solar-plus-storage project
By GridDigest Editorial · June 13, 2026 · synthesized from 3 sources

Ark Energy has received approval from AEMO and Transgrid to connect its Richmond Valley solar-plus-storage facility in New South Wales to the National Electricity Market. The project comprises 435MW of solar capacity and 3,148MWh of battery storage.
Ark Energy has secured regulatory approval to connect its Richmond Valley solar-plus-storage project in New South Wales to Australia's National Electricity Market, marking a significant milestone for one of the state's larger planned clean energy developments.
Project Approval and Grid Connection
The Australian Energy Market Operator (AEMO) and transmission network operator Transgrid have both granted connection approval for Ark Energy's Richmond Valley Solar Farm and Battery Energy Storage System (BESS). The project will feed power into the NEM upon completion, adding utility-scale renewable generation and storage capacity to the New South Wales grid.
Capacity and Scale
The sources report the project's solar generation capacity at 435MW. On the storage side, two of the three source reports cite a battery capacity of 3,148MWh, while the project is also described elsewhere as a 3.1GWh facility — a figure consistent with that megawatt-hour total when rounded. Together, the solar and storage components position Richmond Valley as a substantial combined-cycle renewable asset for the region.
Context for NSW Renewable Development
The Richmond Valley project's grid connection approval represents a concrete step forward in the buildout of large-scale solar-plus-storage infrastructure in New South Wales, a state working to expand its renewable energy capacity as older thermal generation retires. Securing sign-off from both AEMO and Transgrid is a prerequisite for projects to proceed toward construction and eventual commercial operation on the NEM. The dual approval confirms the project has met the technical and regulatory requirements set by the market operator and the relevant transmission network service provider for the region.
Ark Energy has not publicly detailed a construction timeline in the materials reviewed, but the connection approvals remove a key procedural hurdle that precedes project development moving into later stages.
Sources (3)
Methodology: Synthesized from three source reports covering the same project approval announcement, reconciling capacity figures and details across all three sources.